“Time is money” has particular significance on projects. Organizations invest money, effort, and resources because they expect a project to deliver value. When completion slips, the revenue, operational benefits, or essential services tied to that completion can slip with it. Finishing earlier can therefore increase the value of the investment.
Stephen Devaux, the creator of Critical Path DRAG, argues that Critical Path Method (CPM) scheduling left an essential measurement uncalculated: how much time each critical activity adds to project duration.
Stottler Henke has worked with Devaux to bring that measurement to Aurora through Critical Path DRAG analysis, helping teams connect schedule improvement opportunities to project value.
What difference would it make if a 50-week project finished in 45 weeks, or a two-week project took four? The answer depends on what earlier or later completion means for the organization.
For a product launch, delay could mean missing a seasonal sales opportunity. During a plant shutdown, each additional day can mean hundreds of thousands of dollars in lost revenue. For a hospital construction project, earlier completion means earlier access to care.
Devaux’s central point is that project duration deserves attention because it affects the value delivered. Understanding that relationship helps teams assess whether spending more to finish earlier is worthwhile.
A project’s completion time is determined by the interplay of activities, dependencies, lags, constraints, and resource limitations that collectively govern how quickly the project can be completed.
Identifying the critical path is an essential first step in accelerating a project. However, simply knowing that an activity is critical does not reveal how much reducing a critical path’s duration will shorten the overall project.
Critical Path DRAG addresses this limitation by quantifying how much each critical-path activity contributes to the project’s total duration. Importantly, an activity with a long duration may have relatively little DRAG because shortening it beyond a certain point causes another path to become critical, limiting the benefit to the overall project.
This distinction is essential for making effective schedule compression decisions. Rather than focusing simply on the longest or most visible critical activities, project managers can use DRAG to identify where schedule improvements will have the greatest impact on project completion, enabling more targeted and cost-effective investments in project acceleration.
Consider an example from Devaux: should a team spend $20,000 to shorten Critical Path Activity #187 by twelve days, or $30,000 to shorten Activity #422 by six days?
The first option appears less expensive and offers a larger activity-duration reduction. But suppose Activity #187 has only two days of DRAG, while Activity #422 has six.
Shortening the first activity alone would offer only two days of project compression. Shortening the second could offer six. Comparing activity-duration reductions without their DRAG values could therefore lead to the wrong investment.
Drag cost adds another input: what those saved project days are worth. Teams can compare that value with the expense, feasibility, and risk of achieving the reduction.
Aurora makes Critical Path DRAG analysis accessible through its built-in analytics capabilities, helping project managers identify which activities offer the greatest opportunities to shorten overall project duration.
Users simply select Analyze Critical Path Drag from Aurora’s Analytics menu. Aurora automatically calculates DRAG values and presents the results in a Tabular Editor and two Gantt charts, making it easy to examine both individual activities and their impact on the overall schedule.
One Gantt view shows only critical path tasks. Tasks without DRAG appear solid red; tasks with DRAG include an internal white line indicating the available DRAG.
By combining DRAG calculations with interactive schedule visualization, Aurora helps project managers move beyond simply identifying critical activities to identifying and prioritizing opportunities for project acceleration. When combined with the economic value of earlier completion, these insights support better-informed decisions about where to invest resources to achieve the greatest project benefit.