Why Resource-Loaded Scheduling is Hard: Combinatorial Scaling Prevents Exhaustive Search

Book a Demo

Why Resource-Loaded Scheduling Is Hard: The Impact of Choice

If the shortest possible project schedule exists, why can’t scheduling software simply find it? Why can different systems produce schedules with different completion dates for the same project?

The difficulty comes from choice. When activities compete for limited resources, the order in which they are scheduled can affect the project’s duration. Exploring every possible ordering quickly becomes impractical—even for a relatively small number of activities.

Our video, “Why Scheduling Is Hard: Combinatorial Scaling Prevents Exhaustive Search,” explains how these choices multiply and why heuristic scheduling is important for addressing complex scheduling problems.

Limited Resources Introduce Choices

Consider a schedule defined only by activity durations and precedence relationships, without resource limitations. Calculating its earliest completion is computationally straightforward.

Resource constraints change the problem. If two activities need the same resource and cannot run simultaneously, the scheduler must determine which goes first. That decision can affect when subsequent activities begin and when the project finishes.

The challenge grows when activities require different combinations of people, equipment, facilities, or other resources. Giving one activity access to a shared resource may delay another activity and the work that follows it.

How Quickly Do the Possibilities Multiply?

For three activities that can be ordered freely, there are six possible sequences. See the image below and the video.

Adding a fourth activity creates 24 sequences because it can occupy four positions in each existing sequence.

This growth follows a factorial: for n freely ordered activities, there are n! possible sequences.

 

Activities Possible Orderings
3 6
5 120
10 3,628,800
20 Approximately 2.43 quintillion

 

A few million possibilities may sound manageable for a computer. But factorial growth quickly outpaces computing speed.

Even at a hypothetical rate of 10 million orderings per second, checking every ordering of 20 activities would take more than 7,000 years.

This illustrates why simply trying every possibility and selecting the best result is not a practical general approach.

Project Structure Matters

Not every project with 20 activities has 20 freely ordered activities. Precedence relationships restrict which sequences are valid, reducing the choices available.

Order also does not always affect overall duration. For example, if independent activities all require the same single resource, run one at a time, and have no additional restrictions, rearranging them does not change the total time required.

However, that simplicity is fragile. Add a second resource with limited availability, different resource quantities, or timing restrictions, and activity order may affect the outcome again.

The number of activities alone therefore does not determine scheduling difficulty. The relationships, resource requirements, and timing restrictions within the model matter too.

Why Heuristic Scheduling Matters

Heuristic scheduling uses knowledge about the problem’s structure to guide scheduling decisions and focus on promising choices.

Instead of exhaustively evaluating every ordering, a heuristic approach narrows the search. The quality of those decisions helps explain why scheduling systems can produce different project durations from the same inputs.

For resource-loaded projects, finding a useful schedule requires more than calculating dates. It requires making effective choices about competing activities and limited resources within a practical amount of time.

Watch “Why Scheduling Is Hard: Combinatorial Scaling Prevents Exhaustive Search” for a visual explanation of how scheduling choices multiply and why they matter.

Would you like a FREE Demo? Contact Us

Please enter your contact details, company name and a short message below and we will answer your query as soon as possible.

Contact Us