Introduction to Critical Path DRAG and DRAG Cost

Download Aurora-Viewer

Last month, Critical Path DRAG functionality was added to both the Aurora-Viewer and the full version of AURORA. Aurora-Viewer is the only option known to us that provides Critical Path DRAG calculations via a FREE tool. Even though Critical Path DRAG and DRAG Cost are both included in the PMBOK Guide 8, they are rarely found in any software, let alone free software like Aurora-Viewer.

What is Critical Path DRAG?

Two activities can sit on the critical path and offer very different opportunities to shorten the project. 

Critical Path DRAG: measures how much time each critical path activity adds to the finish date.

 

DRAG Cost: estimates what that time costs the project.

 

In particular, the DRAG cost of an activity can have immeasurable implications for customers; this is the amount of value that a project loses as a result of delivery delays from an activity’s Critical Path DRAG. Meeting a project delivery date is always dependent on the project’s longest critical path, thereby determining its earliest finish. 

If an activity is not on the critical path, critical path theory calculates total float. Total float tells you the maximum amount of time an activity can slip before making its path the longest in the project. Critical Path DRAG tells you how much sooner the project could finish if you shortened a particular critical activity, with the rest of the schedule held constant. In Figure 1, we illustrate an example of a simple network showing drag, where total float (or total slack) is represented by TF and DRAG is represented by D. 

Figure 1. Simple Network Showing DRAG.

 

Figure 2 shows an example from Stephen A. Devaux’s 2012 article “The DRAG Efficient: The Missing Quantification of Time on the Critical Path,” in the U.S. Department of Defense (DOD) publication Defense AT&L Magazine. In this example, the project is due on day 45, but the schedule shows it finishing on day 60, 15 days late. Follow the red arrows in Figure 2 to see why. The tasks on that route, A through E, add up to 60 days.

 

Figure 2. The critical path puts the scheduled finish on day 60, against a day-45 deadline. Early and late ranges show each task’s start and finish days. Adapted from Stephen A. Devaux.

 

How to Calculate Critical Path DRAG

 

Critical Path DRAG measures how much sooner the project could finish if you shortened one task on the critical path and kept the rest of the schedule as planned. Figure 3 shows how much time each critical task is adding to the 60-day schedule.

Figure 3. Activity DRAG on the critical path and total float on the parallel paths. Adapted from Stephen A. Devaux.

 

Look at Task C, which takes 20 days. Shortening it to 17 days brings the project finish forward from day 60 to day 57. Now both routes, the one through C and the one through I, take 57 days. If you shorten C again, the route through I still takes 57 days. That’s why C has just three days of DRAG.

Task D takes only five days. Both routes through C and I pass through D, so shortening D saves time on both. In this example, D has five days of DRAG. Once you try a change, recalculate the schedule to see which route now determines the finish.

What is DRAG Cost?

DRAG Cost estimates what the time added by a task costs the project.

 

A later finish might mean paying for equipment for longer or waiting longer to earn revenue. In Figure 4, every day past the day-45 deadline costs $10,000.

Figure 4. Activity-level DRAG Cost at $10,000 per day of delay beyond day 45. Adapted from Stephen A. Devaux.

 

Task E has 15 days of DRAG. At $10,000 per day, that gives it a DRAG Cost of $150,000. In Devaux’s example, doubling the resources assigned to E each day cuts its duration from 15 days to 10 and brings the project finish forward to day 55. E’s budget rises from $20,000 to $26,700, while the project saves $50,000 in delay costs. After the $6,700 in additional spending, the net savings are $43,300.

Figure 4 evaluates each task on its own. To calculate the total cost of finishing on day 60, multiply the project’s 15 days of delay by $10,000 per day.

Critical Path DRAG and DRAG Cost in Aurora

In Devaux’s example, Task C takes 20 days, but shortening it can move the project finish forward by only three days. Shortening Task E by five days, on the other hand, saves $50,000 in delay costs at an additional cost of $6,700. That’s the value of looking at both metrics. Critical Path DRAG shows how much sooner the project could finish, and DRAG Cost helps you decide whether getting there sooner is worth the extra expense.

The full version of AURORA supports both metrics. The free Aurora-Viewer supports them for critical path activities whose incoming and outgoing links are all finish-to-start, with no leads or lags. Figure 5 shows a simple network with Critical Path DRAG calculated and represented graphically by the white inset and textually via the value in hours shown at the bottom right of the red critical path activities.

Figure 5. Activity DRAG on the critical path shown textually & visually in Aurora-Viewer.

 

If you’re reviewing a Primavera P6 schedule, download Aurora-Viewer and run Critical Path DRAG analysis from the Analytics menu to see which activities offer room to bring the finish date forward.