Aurora is Applied to Refinery Turnaround

Solving the World’s Most Challenging Project Management and Scheduling Problems More Efficiently

Aurora continues to solve many of the world’s most challenging project management and resource-constrained scheduling problems more optimally than any other solution.

The image below illustrates the benefits of applying Aurora to the complex project management domain of refinery turnaround. Similar benefits are available to other types of maintenance, repair, and overhaul (MRO) situations, such as plant maintenance or aircraft MRO.

Benefits of Using Advanced Scheduling Technology With Primavera P6 Versus  Resource-Leveling Only

Primavera P6 Enterprise Project Portfolio Management is a powerful, robust, and easy to use solution for globally prioritizing, planning, managing and executing projects, programs and portfolios. Primavera P6 Enterprise Project Portfolio Management is an integrated project portfolio management (PPM) solution comprising role-specific functionality to satisfy each team member’s needs, responsibilities and skills.

Primavera P6 provide a resource leveling capability. The goal of resource leveling in Primavera P6 is to provide the user with a valid resource loaded schedule that does not have any over allocated resources. Primavera P6 does not optimize the allocation of resources in order to generate the shortest resource leveled schedule. Even though Primavera P6 does not optimizethe the schedule, it is likely many users of Primavera P6 are NOT aware that the results from the resource leveling process are not optimal, and could be improved upon significantly.

  • Resource leveling will refer to the functionality provided in Primavera P6 and other commercial project management software, and
  • Advanced scheduling technology or intelligent scheduling will refer to resource-constrained scheduling that attempts to optimize the utilization of resources to minimize the project duration. For projects that are time critical/resource intensive, advanced scheduling technology can significantly shorten the project duration.
    • Aurora is an intelligent advanced scheduling engine that can be utilized independently or in conjunction with other tools such as Primavera P6 to generate shorter schedules. The following will illustrate these benefits via the analysis of a real refinery turnaround project.

REFINERY TURNAROUND LEVERAGING ADVANCED SCHEDULING TECHNOLOGY

  • Primavera P6 only (utilizing its resource-leveling capability), and
  • Primavera P6 leveraging Aurora’s advanced scheduling technology.

The project network consists of over 2,500 activities. A view of the network is shown below.

Turnaround Project Network

The results of the analyses are a follows:

  • Primavera P6 resource-leveling: 67 days, 3 hours
  • Primavera P6 leveraging Aurora Advanced Scheduling: 56 days, 6 hours, 30 minutes

The difference is absolute terms is over 10.5 days. There are a few ways to compare these results; the simplest is to simply compare overall durations, using the Aurora Advanced Scheduling results as the basis:

  • Primavera P6 resource-leveling is 19.3% longer than Aurora (67.125 – 56.27) / 56.27
  • Using the P6 resource-leveling as the bases:
    • Aurora Advanced Scheduling is 16.2% shorter than Primavera P6 resource-leveling (67.125 – 56.27) / 67.125

Another valuable perspective is comparing the resource-constrained result with the Critical Path that is the situation assuming unlimited resources. Why is this perspective valuable? Because the Critical Path is the best case scenario, and the valid schedule when considering resources must always be longer than the Critical Path, so the length longer than the Critical Path is the only portion of the total project duration that the resource- leveling or advanced scheduling can effect.

The Critical Path for the refinery turnaround project is 46 days.

Primavera P6 resource-leveling results longer than Critical Path 21.125 days

Percent longer than Critical Path 45.9% 21.125 / 46

Primavera P6 leveraging Aurora Advanced Scheduling results longer than Critical Path 10.27 days

Percent longer than Critical Path 22 % 10.27 / 46

The percent difference between days more than Critical Path for resource leveling and advanced scheduling is 105.70% (21.125 – 10.27) / 10.27

All the results demonstrate the significant benefit of leveraging Aurora advanced scheduling in conjunction with Primavera P6. Recall that everything besides the method for scheduling is that same in both cases. Leveraging Aurora saved over 10.5 days, and all the associated costs with all the resources that are needed, as well as the lost revenue from the refinery being unavailable.

Cost savings and other benefits of leveraging Aurora are huge for the initial plan,

BUT

even more potential benefit comes in the execution phase of the project, where unexpected circumstances need to be dealt with. By leveraging Aurora’s intelligence rescheduling can by done quickly and the updated schedule will be shorter than if one used resource-leveling only. Therefore, every time a re-schedule is performed the overall benefit of leveraging Aurora increases.

Aurora Scheduling Software Enables On-Time Aircraft Deliveries

Building next-generation aircraft may be a daunting task logistically, but using new software developed with Missile Defense Agency (MDA) funding could save manufacturers time, cost, and labor, ensuring quicker deliveries around the world.

Stottler Henke Associates of San Mateo, CA originally developed its Aurora™ scheduling technology for NASA to use in managing the timing of International Space Station construction. After serving NASA, Stottler Henke upgraded Aurora’s capabilities with new algorithms developed for missile defense engagement planning.

The enhancements were funded through an MDA Small Business Innovation Research (SBIR) Phase I contract in 2006, and a Phase II contract in 2008. The company was awarded a multi-million-dollar contract from the Boeing Company following the release of a benchmark study Boeing conducted. The study concluded that Aurora was more efficient in managing resources than the system used by Boeing for almost two decades. Stottler Henke’s technology is now the primary scheduling tool for production of Boeing 787 aircraft.

Stottler Henke’s challenge was to improve the manufacturing efficiencies of Boeing’s 787 project by optimizing aircraft assembly schedules through the use of software designed for better resource management — from equipment to personnel. The problem could be tackled only after fully realizing the scope of Boeing’s operation.

In operational tests, Aurora reduced the amount of time needed on Boeing 787 construction projects through a more efficient use of resources by 10 percent to 30 percent over other commercial schedulers.

How it Works

Initially, the central problem Boeing faced was a lack of space due to a large number of workers manning stations around the center part of a fuselage where the wings were being mounted, while fewer workers were busy elsewhere on the aircraft. So Boeing first asked Stottler Henke to program Aurora for optimal assignment of workers during production of a generic 787. The programming took into account that only a limited number of people could work in a given area to ensure safety and to ensure that tasks would be performed properly. Once Stottler Henke had completed the programming for a generic 787, Boeing created additional configurations to meet the specifications of purchasing airlines. Such airline- specific scheduling continues today at Boeing, aided by the efficiencies of Aurora software.

Design of the Aurora software is based on the premise that order is the key to success. A company like Boeing might be working on several large projects in its assembly plant, but corporate executives are well aware that each large project requires completion of many small tasks, in a certain order, and within prescribed time limits. Most advanced scheduling systems competing with Aurora can crunch such data without much of a problem. But none of them uses intelligent breakdowns of data, including variables that can change the entire picture of how time and labor need to be distributed.

Aurora offers companies more than just a simple schedule for best managing a project’s tasks. Using corporate data that is input into Aurora, the software can analyze the full potential of the workforce based on skills, work shifts, staffing requirements for certain tasks, actual working space where a task is being conducted, and perhaps most importantly, keeping the workflow in sync with schedule completion requirements. A company can also use the program to interchange variables such as the ordering of projects or staffing requirements on certain tasks to develop a production schedule that best suits specific corporate interests.

Where it Stands

Stottler Henke continues to look beyond the Boeing contract, seeking to have Aurora in many aerospace manufacturing and repair centers across the country. The company most recently contracted to provide scheduling services for a division of Acument Aerospace Technologies, which makes aircraft fasteners and bolts for many manufacturers, including Boeing.

Outside of the company’s aerospace contracts and success, the company would entertain partnerships with companies that desire high-quality scheduling models as part of their software systems.

More Information

For more information on Stottler Henke’s Aurora system, visit http://info.hotims.com/22928-517. (Source: Joe Singleton/NTTC; MDA TechUpdate, Missile Defense Agency, National Technology Transfer Center Washington Operations)