October 2026: Aurora Intelligent Scheduling & Project Management Newsletter

Check out our October 2026 Aurora Intelligent Scheduling and Project Management Newsletter, featuring the latest improvements to Aurora and the free Aurora-Viewer. This issue highlights new Critical Path DRAG functionality, how DRAG analysis can help identify opportunities to shorten project duration, and enhancements to performance tracking and visualization.

  • Critical Path DRAG analysis, now available in both Aurora-Viewer and the full version of Aurora.
  • How DRAG measures each critical activity’s contribution to project duration, helping project managers identify opportunities to shorten schedules, broken down by Stephen Devaux, the inventor of Critical Path DRAG.
  • New Tabular Editor and Gantt chart views that display activity DRAG values.

Explore the latest Aurora developments and download Aurora-Viewer to try its newest features for FREE!

September 2026: Aurora Intelligent Scheduling & Project Management Newsletter

Check out our September 2026 Aurora Intelligent Scheduling and Project Management Newsletter, featuring Aurora’s latest activities and developments in intelligent scheduling. This issue highlights Aurora at the NCMS Sustainment Accelerator, Aurora-based software supporting Satellite Control Network operations, advanced project planning and modeling capabilities, and the latest improvements to the free Aurora-Viewer.

  • Aurora Featured at the NCMS Sustainment Accelerator at Puget Sound Naval Shipyard & Intermediate Maintenance Facility
  • Aurora-Based MARS / AST Scheduling System Entered Worldwide Operational Use by the U.S. Space Force
  • Advanced Project Planning and Modeling Features Not Available in Other Conventional Project Management / Scheduling Software
  • Aurora-Viewer Improvements: Expanded Visualization Functionalities

Explore the latest Aurora developments and download Aurora-Viewer to try its newest features for free.

Aurora Featured at 2026 NCMS Sustainment Accelerator at Puget Sound Naval Shipyard

Stottler Henke exhibited Aurora at the NCMS Sustainment Accelerator at Puget Sound Naval Shipyard & Intermediate Maintenance Facility in Bremerton, Washington, August 25–27. The event brought together Navy stakeholders and industry to explore technologies that can help address shipbuilding, maintenance, and sustainment challenges.

During the event, Stottler Henke covered some of the benefits of applying Aurora Intelligent Scheduling to Real-World Problems:

  • Optimizes schedules automatically by considering task dependencies, priorities, limited resources, skills, shifts, equipment, facilities, and other operational constraints.
  • Improves resource utilization and reduces schedule duration, helping organizations accomplish more with existing personnel, equipment, and infrastructure.
  • Creates more realistic and executable schedules by modeling real-world constraints that conventional project-management systems often cannot represent effectively.
  • Dynamically reschedules when conditions change, including emergent work, resource disruptions, shifting priorities, and changing operational requirements.
  • Identifies bottlenecks and supports rapid “what-if” analysis, giving managers better decision support before committing resources or changing plans.

Aurora Intelligent Scheduling

July 2026: Aurora Intelligent Scheduling & Project Management Newsletter

Check out our July 2026 Aurora Intelligent Scheduling and Project Management Newsletter, where we explore 16 powerful real-world project modeling capabilities available in Aurora and highlight the latest features and benefits of the free Aurora-Viewer for Primavera P6 XER files.

Explore how Aurora can model complex real-world project conditions and try Aurora-Viewer for free!

Stottler Henke Presents at the 2026 National Shipbuilding Research Program (NSRP) Business Technologies Panel Meeting

Aurora and the free Aurora-Viewer were presented at the National Shipbuilding Research Program (NSRP) Business Technologies Panel Meeting, held at the U.S. Coast Guard Yard Baltimore, June 23-24.

The presentation highlighted Aurora’s intelligent resource scheduling capabilities and their potential benefits for ship maintenance scheduling and ship construction scheduling, including improving resource utilization and project throughput. Attendees were also introduced to Aurora-Viewer, the free Primavera P6 XER file viewer for Windows.

The Coast Guard’s sustainment enterprise is operating in an increasingly complex environment. Aging platforms, evolving mission requirements, modernization efforts, workforce challenges, and supply chain pressures all affect how maintenance and lifecycle support are planned and executed. Aurora can help address these challenges through advanced resource scheduling that accounts for real-world constraints, competing priorities, and changing conditions during execution.

June 2026: Aurora-Viewer, Free Primavera P6 XER File Viewer UPDATE

The Free Aurora-Viewer for XER files has been expanded with more capabilities. Thank you for the feedback!

This 2026-June release adds new schedule analysis, reporting capabilities, and more.

Highlights include:

  • Utilities > Run Logic Checks
    • Runs a set of model analysis methods to catch common modeling problems.
  • Utilities > Find Redundant Constraints
    • Shows redundant constraints.
  • Reports > DCMA Report
    • Shows a subset of the 14 DCMA audits.
  • Reports > Critical Path Predecessor Chart
    • Shows how many tasks on the critical path have a certain number of predecessors. This provides insight into how much of the longest path through the network is susceptible to integration risk / merge bias. Integration risk / merge bias is the risk that one or more tasks feeding a successor task will be late, thereby delaying the start of the successor task. Since the successor task is part of the critical path, then any predecessor delay will directly affect the end date of the project.
  • File > Open XER (if includes Greek characters)
    • Users can now open XER files where the text includes Greek characters. When such files are imported, the text, e.g., activity names, will be displayed correctly across the Aurora UI.

Aurora-Viewer is a free Windows-based tool for viewing Primavera P6 XER schedules—based on the Aurora intelligent scheduling and project management software.

Download Aurora-Viewer here.

Have feedback or feature ideas? We’d love to hear from you through the feedback form on the Aurora-Viewer page.

April 2026: Aurora-Viewer, Free Primavera P6 XER File Viewer UPDATE

Aurora-Viewer continues to improve—thank you for all the valuable feedback!

The latest version (April 2026 update) of Aurora-Viewer:

  • Reads critical path information directly from the XER file during import
    • Tasks on the critical path are displayed in red, in both the PERT and Gantt charts
    • Tasks with negative float are also shown in red, in both the PERT and Gantt charts
  • Adds a new Float section to the Project Model Overview Report, including:
    • Number of Zero Float Activities
    • Number of Negative Float Activities

Aurora-Viewer is a free Windows-based tool for viewing Primavera P6 XER schedules—no Primavera license required.

You can access Aurora-Viewer here.

We’re always working to improve Aurora-Viewer, so share your experience with us by filling out a feedback form at the bottom of the Aurora-Viewer page!

March 2026: Aurora-Viewer, Free Primavera P6 XER File Viewer UPDATE

The free Windows-based viewer for Primavera P6 XER files, Aurora-Viewer, has been improved again. We appreciate all your helpful feedback!

Aurora-Viewer allows users to open and view Primavera P6 schedules in the “.XER” file format, without needing a full Primavera license; for FREE.

The latest version (updated March 2026) of Aurora-Viewer:

  • Displays activities on the critical path in red, in both the PERT and Gantt charts
  • The colors of links for the constraint types have been updated to:
    • Finish-to-Start (FS) – Black
    • Start-to-Start (SS) – Blue
    • Finish-to-Finish (FF) – Green
    • Start-to-Finish (SF) – Red
  • A ‘Total Float’ column has been added to both the Tabular Editor and the Tabular Gantt

The installation includes a ‘videos’ subfolder with demonstration videos. The Single-Element-Display video provides helpful guidance for navigating and understanding your schedule.

You can access Aurora-Viewer here.

We are continually improving Aurora-Viewer and welcome your suggestions for the next iteration!

Stottler Henke Presents at the 2026 Construction CPM Conference

Stottler Henke will present “Benefits of Additional Real-World CPM Modeling Capabilities with Aurora” at the Construction CPM Conference, January 18–21, at the Grand Sierra Resort in Reno, Nevada. The Construction CPM Conference brings together professional planners and schedulers to share knowledge and explore developments in Critical Path Method (CPM) scheduling, project controls, scheduling software, and related practices.

January 2026: Aurora Intelligent Scheduling & Project Management Newsletter

Check out our January 2026 Aurora Intelligent Scheduling and Project Management Newsletter, featuring the latest update to Aurora-Viewer, our free Primavera P6 XER file viewer. We also highlight key Aurora features and benefits available to preview in Aurora-Viewer and explore how Aurora’s advanced scheduling capabilities can complement Primavera P6.

Try the latest version of Aurora-Viewer and help shape future updates by sharing your thoughts through the feedback form at the bottom of the page!